SAMPLE LEAD TIME
Layers | Urgent | Standard |
Single, Double side board | 2 days | 3~5 days |
4-Layers board | 3 days | 5~7 days |
6-Layers board | 4 days | 8~10 days |
8-Layers board | 5 days | 10~12 days |
10~12-Layers board | 8 days | 15~18 days |
MASS PRODUCTS LEAD TIME
Layers | Standard |
Single, Double side board | 8~10 days |
4-Layers board | 2~3 weeks |
6-Layers board | 3~4 weeks |
8-Layers board | 3~4 weeks |
10~12-Layers board | 5~6 weeks |
- The lead time depending the layers
- The lead time need one more day for new projects